KHNP, consortium fail to agree on Czech nuclear plant contract
Summary
Korea Hydro & Nuclear Power (KHNP) ended contract negotiations with the Daewoo E&C and Doosan Enerbility consortium at the Dukovany site in the Czech Republic on Thursday after failing to agree on key terms. KHNP plans to select a replacement contractor through competitive bidding by July 2027. The dispute centered on contract structure, work scope, baseline quantities and construction costs. The two APR1000 reactors are scheduled to begin full construction in November 2029 and be completed in 2039 and 2040.
Key Facts
- KHNP signed the main contract with Czech state-run project company Elektrarna Dukovany II in June 2025, after submitting its final bid in April 2024.
- KHNP proposed a lump-sum contract based on quantities established at the basic design stage, while the consortium sought payment adjustments based on quantities determined during detailed design.
- A dispute resolution committee met 11 times in July, followed by senior-level talks in September and October, but the sides did not reach an agreement.
- KHNP scheduled a briefing for prospective bidders for January and plans to open bidding in April, though the detailed process and timeline have not been finalized.
- Daewoo E&C said it submitted a revised proposal at a reduced price and requested that the negotiation deadline be extended to Dec. 31.
Dispute over pricing, construction terms prompts search for new builder

An aerial view of the planned site for new nuclear reactors in Dukovany, Czech Republic / Courtesy of Korea Hydro & Nuclear Power
Korea Hydro & Nuclear Power (KHNP) announced Thursday that it had ended negotiations with a consortium of Daewoo E&C and Doosan Enerbility over a construction contract for a 26 trillion won ($19.4 billion) nuclear power project in the Czech Republic, after the two sides failed to reach an agreement on key terms.
KHNP said it would begin terminating its cooperation agreement with the consortium and prepare a competitive bidding process to select a new contractor, seeking to minimize disruption to construction of the two Korean-designed APR1000 reactors at the country’s Dukovany site.
“KHNP and the construction consortium had worked to reach an amicable agreement through working-level negotiations, a dispute mediation committee and management-level talks, but failed to reach a final agreement,” the state-run nuclear operator said.
The breakdown follows about 15 months of negotiations after KHNP signed the main contract with Elektrarna Dukovany II, the Czech state-run company in charge of the project, in June 2025.
KHNP said the two sides had already been at odds over key contract terms when KHNP submitted its final bid in April 2024, and failed to resolve their differences even after months of further talks.
It explained that the dispute involved not only construction costs but also the contract structure, scope of work, baseline quantities and how the main contract’s terms would be reflected in the construction contract.
KHNP proposed a lump sum contract based on baseline quantities established at the basic design stage, arguing that it would align the construction contract with the main project agreement and provide greater cost certainty.
However, the consortium sought to adjust payments based on quantities determined at the detailed design stage, including increases in construction volumes.
The company said it had revised its proposal to account for additional work and requested detailed cost breakdowns to assess the proposed construction price. Despite a dispute resolution committee that met 11 times in July and further talks between senior executives in September and October, the two sides failed to bridge their differences.

Korea Hydro & Nuclear Power's headquarters in Gyeongju, North Gyeongsang Province / Korea Times file
KHNP plans to select a replacement contractor by July 2027, with a briefing for prospective bidders scheduled for January and bidding set to open in April, although the detailed process and timeline have not been finalized.
The company said it would work closely with the Czech project owner to keep the project on schedule, with site preparation due to begin in January 2028 and full construction scheduled to start in November 2029. The two reactors are slated for completion in 2039 and 2040, respectively.
KHNP said the Czech government was already aware of the situation and it was in close talks with the Czech project company about selecting a new contractor and other details.
“We are discussing the issues with the Czech’s Industry Ministry,” the company’s Executive Vice-President Choi Il-kyung said during a briefing at Government Complex Sejong on the day.
“The Czech government respects our position. It also understands that we need to resolve the situation at this point and select a replacement contractor.”
When questioned about public opinion in the Czech Republic and across the European Union as factors to watch, KHNP said it will cooperate closely with the Czech government to maintain public confidence and support for the project.
While selecting a new contractor, KHNP would handle key tasks, including design, permitting and project management, or outsource them to other companies.
Daewoo E&C expressed regret over KHNP’s decision and called for negotiations to resume, saying it had submitted a revised contract proposal at “a reduced price, despite the losses it would incur.”
The company said KHNP introduced revised contract terms on Oct. 7, but failed to allow sufficient time for review before ending negotiations, adding the consortium had formally requested an extension of the deadline to Dec. 31.
“Requiring the construction consortium to finalize its position and conclude negotiations within just three weeks was simply unrealistic,” Daewoo E&C said, citing the need for thorough assessments of costs, construction schedules and work scope for the first commercial reactor using the APR1000 design.
The company also criticized KHNP’s proposed lump sum contract, arguing that it would leave the builders bearing a substantial share of additional costs arising from design changes, despite their limited involvement in the design process.
“We ask KHNP to resume negotiations with the construction consortium in good faith, in the broader interest of the project and the national interest,” it said.